Restructured Electricity Markets:
Three States' Experiences in Adding Generating Capacity
GAO-02-427: Published: May 24, 2002. Publicly Released: Jun 24, 2002.
Additional Materials:
- Full Report:
- Accessible Text:
Contact:
(202) 512-6877
contact@gao.gov
Office of Public Affairs
(202) 512-4800
youngc1@gao.gov
Twenty-four states and the District of Columbia have restructured electricity markets by shifting from service provided through a regulated monopoly to service provided through open competition among the local utilities and their competitors. The restructuring was intended to boost competition and expand consumer choice, increase efficiency, and lower prices. Of the three states GAO studied, Texas had the greatest need for additional electric power, and it added the most new capacity from 1995 through 2001. In contrast, California added 25 percent of the forecasted need for capacity over this period. Although Pennsylvania added less than half of its forecasted need for capacity, the state continues to be a net exporter of electricity to nearby states. The three states have similar processes for approving applications to build and operate new power plants. In all three states, state and local agencies must review the applications to ensure that the developer complies with environmental, land use, and other requirements before issuing the permits necessary to build and operate a power plant. California also has a state energy commission that reviews each power plant application to determine whether the benefits of additional electricity outweigh its likely negative environmental or other effects. Texas' rules for connecting new power plants to the electricity transmission system are less costly for independent developers and are administratively simpler than the approaches used in California and Pennsylvania. In deciding where to build new power plants, independent developers said they weigh a market's risks, including uncertainty about changes in a state's market rules, against expected profits. Higher risks require higher expected profits.
Recommendations for Executive Action
Status: Closed - Implemented
Comments: On July 24, 2003, FERC issued its final rule entitled "Standardization of Generator Interconnection Agreements and Procedures." The rule requires that public utilities provide independent power developers with access to their grid by using FERC's standard interconnection agreement.
Recommendation: To facilitate development of power plants needed in restructured markets and to provide comparable treatment for all developers, the Chairman of the Federal Energy Regulatory Commission, in consultation with transmission system owners, power plant developers, and lenders, should develop and require the use of a standardized interconnection agreement.
Agency Affected: Federal Energy Regulatory Commission
Status: Closed - Implemented
Comments: On July 28, 2004, FERC reported that it has taken several steps--in consultation with transmission system owners and other stakeholers--to clarify how transmission upgrade costs are allocated. Most importantly, on July 24, 2003, FERC issued Order No. 2003, in which it established generic rules for the interconnection of generation plants with capacity in excess of 20 MW to the transmission grid.
Recommendation: To facilitate development of power plants needed in restructured markets and to provide comparable treatment for all developers, the Chairman of the Federal Energy Regulatory Commission, in consultation with transmission system owners, power plant developers, and lenders, should clarify how transmission system upgrade costs are allocated.
Agency Affected: Federal Energy Regulatory Commission
Explore the full database of GAO's Open Recommendations
»
Dec 10, 2020
-
Uranium Management:
Actions to Mitigate Risks to Domestic Supply Chain Could Be Better Planned and CoordinatedGAO-21-28: Published: Dec 10, 2020. Publicly Released: Dec 10, 2020.
Dec 8, 2020
-
Offshore Wind Energy:
Planned Projects May Lead to Construction of New Vessels in the U.S., but Industry Has Made Few Decisions amid UncertaintiesGAO-21-153: Published: Dec 8, 2020. Publicly Released: Dec 8, 2020.
Nov 19, 2020
-
Nuclear Waste Disposal:
Better Planning Needed to Avoid Potential Disruptions at Waste Isolation Pilot PlantGAO-21-48: Published: Nov 19, 2020. Publicly Released: Nov 19, 2020.
Oct 29, 2020
-
Nuclear Safety:
DOE and the Safety Board Should Collaborate to Develop a Written Agreement to Enhance OversightGAO-21-141: Published: Oct 29, 2020. Publicly Released: Oct 29, 2020.
Oct 15, 2020
-
Nuclear Weapons:
NNSA Plans to Modernize Critical Depleted Uranium Capabilities and Improve Program ManagementGAO-21-16: Published: Oct 15, 2020. Publicly Released: Oct 15, 2020.
Jul 24, 2020
-
Nuclear Weapons:
Action Needed to Address the W80-4 Warhead Program's Schedule ConstraintsGAO-20-409: Published: Jul 24, 2020. Publicly Released: Jul 24, 2020.
Jun 24, 2020
-
National Nuclear Security Administration:
Analyzing Cost Savings Program Could Result in Wider Use and Additional Contractor EfficienciesGAO-20-451: Published: Jun 24, 2020. Publicly Released: Jun 24, 2020.
Jun 9, 2020
-
Nuclear Weapons:
NNSA Needs to Incorporate Additional Management Controls Over Its Microelectronics ActivitiesGAO-20-357: Published: Jun 9, 2020. Publicly Released: Jun 9, 2020.
May 13, 2020
-
Environmental Liabilities:
DOE Needs to Better Plan for Post-Cleanup Challenges Facing SitesGAO-20-373: Published: May 13, 2020. Publicly Released: May 13, 2020.
May 12, 2020
-
Hanford Waste Treatment Plant:
DOE Is Pursuing Pretreatment Alternatives, but Its Strategy Is Unclear While Costs Continue to RiseGAO-20-363: Published: May 12, 2020. Publicly Released: May 12, 2020.
Looking for more? Browse all our products here