GAO was requested to review the Bonneville Power Administration's (BPA) cost estimates to bury segments of high voltage transmission lines in Montana. Specifically, GAO was asked to: (1) evaluate the validity of the BPA cost data for burying portions of a "twin" 500 KV transmission line; and (2) analyze the general engineering reliability and safety considerations of burying such lines.

GAO found that the BPA estimates of $7.1 to $7.4 million per mile to bury the transmission lines are reasonable. However, because this type of installation is not common, uncertainties exist which could make the actual costs higher or lower. For this reason, little is known about the engineering, reliability, and safety considerations of underground installation for lines of this size.

Mar 20, 2018

Mar 14, 2018

Feb 28, 2018

Feb 16, 2018

Feb 6, 2018

Jan 30, 2018

Dec 7, 2017

Nov 14, 2017

Nov 1, 2017

Oct 26, 2017

Looking for more? Browse all our products here