Lessons Learned from Constructing the Trans-Alaska Oil Pipeline

EMD-78-52: Published: Jun 15, 1978. Publicly Released: Jun 15, 1978.

Additional Materials:

Contact:

Office of Public Affairs
(202) 512-4800
youngc1@gao.gov

In 1968, a feasibility cost study estimated that an oil pipeline system from Prudhoe Bay to Valdez, Alaska, would cost $863 million for a 500,000 barrel-a-day line or $1.046 billion for a 1.2 million barrel-a-day capacity. After construction began in 1975, the Alyeska Pipeline Service Company, the agent for the companies designing and building the pipeline, established a base control budget of about $6.4 billion. By December 1977, this budget had been exceeded by about $1.5 billion. The $19.8 million additional direct labor hours needed to complete the project accounted for most of the $1.5 billion increase.

Several key lessons can be learned from Alyeska's experience and applied to similar future projects: (1) first and subsequent cost estimates should be viewed with skepticism; (2) as much site-specific data as is economically practicable should be obtained; (3) technical and geological uncertainties should be thoroughly investigated; (4) government approval should be contingent on detailed planning for management control, including budgetary controls; and (5) the Alaska natural gas pipeline project's expenditures should have an ongoing government audit to protect the public interest. Alyeska's contract with its execution contractors were reimbursable cost-plus-fixed-fee and fixed overhead; the contractors did not have the financial incentive to minimize costs as they would have had under other contractual arrangements such as fixed-price contracts. Alyeska's experience showed that the no-strike clause in the project labor agreement prevented section-wide or project-wide strikes. Contractor personnel generally interpreted the environmental requirements less restrictively than did government personnel, and Alyeska had to make some adjustments to accomodate the government's interpretation.

Oct 15, 2020

Jul 24, 2020

Jun 24, 2020

Jun 9, 2020

May 13, 2020

May 12, 2020

Apr 29, 2020

  • energy icon, source: Art Explosion

    Priority Open Recommendations:

    Department of Energy
    GAO-20-285PR: Published: Apr 22, 2020. Publicly Released: Apr 29, 2020.

Apr 17, 2020

Mar 11, 2020

Mar 4, 2020

Looking for more? Browse all our products here