Suffolk County Sewer Project Long Island, New York:

Reasons for Cost Increases and Other Matters

CED-77-45: Published: Mar 22, 1977. Publicly Released: Mar 22, 1977.

Additional Materials:


Office of Public Affairs
(202) 512-4800

The Environmental Protection Agency (EPA) granted the Southwest Sewer District of Suffolk County, New York, $135.5 million for construction of a sewer system. Total estimated costs for the system increased about $1 billion from 1969 to 1976.

Inflation was the primary factor causing the overall cost increase. Other factors were a longer than anticipated construction schedule, higher interest rates, and changes in the scope of the project and the cost of engineering services, which were based on a percentage of costs, and therefore increased in proportion to total costs. No violations of applicable regulations in effect at the time were found in the selection of and fees paid to the consulting engineers. The county had performed some limited audits of project costs, but EPA had not. EPA inspected construction for the first time in December 1976. As of November 1976, state reviews were still underway.

Mar 12, 2018

Feb 22, 2018

Jan 26, 2018

Jan 19, 2018

Jan 4, 2018

Dec 22, 2017

Dec 13, 2017

Nov 15, 2017

Nov 2, 2017

Oct 30, 2017

Looking for more? Browse all our products here