The Department of State requests the decision of the Comptroller General as to the availability of appropriated funds for the construction of certain proposed buildings in connection with the Lower Rio Grande Flood Control Project.

While the appropriation does not specifically provide for the construction of buildings, it does provide broadly for construction for the United States portion of the project and, if it be administratively determined that the construction of the buildings in question is essential to the construction and maintenance of the project as authorized by the appropriation, said appropriation may be considered available therefor.

Mar 22, 2018

Mar 20, 2018

Mar 19, 2018

  • Ampcus, Inc.
    We deny the protest.
  • AMAR Health IT, LLC
    We dismiss the protest because our Office does not have jurisdiction to entertain protests of task orders issued under civilian agency multiple-award, indefinite-delivery, indefinite-quantity (IDIQ) contracts that are valued at less than $10 million.
  • Centurum, Inc.--Costs
    We grant the request.

Mar 15, 2018

  • ORBIS Sibro, Inc.
    We sustain the protest in part and deny it in part.