The report you requested was not found, or there is more than one product with this report number. Please select from this list of similar report numbers.


Rolf Jensen & Associates, Inc., B-289475.2; B-289475.3, July 1, 2002 * REDACTION DECISION

B-289475.2,B-289475.3: Jul 1, 2002

Protest that the agency misevaluated the awardee's technical proposal under staffing and past performance subfactors is denied where the record shows that the evaluation was reasonable. Protest that the agency did not accept the protester's proposed indirect rates in the agency's cost realism evaluation is denied where the record shows that the protester was not prejudiced. Even assuming the prote...

  • html report icon View Decision (HTML)
Rolf Jensen & Associates, Inc.

B-289475.2,B-289475.3: Jul 1, 2002

A firm protested a Department of Transportation contract award for fire safety engineering services, contending that Transportation (1) improperly evaluated its technical proposal under staffing and past performance measures, and (2) did not accept the protester's proposed indirect rates in the cost realism evaluation. GAO held that Transportation (1) properly evaluated the protester's technical p...

U.S. Government Accountability Office (GAO)
  • Press Center
  • Copyright & Terms of Use
  • FOIA Requests
  • Contact Us
  • Privacy Policy
  • Scam Alerts
  • Inspector General
  • Accessibility
  • No FEAR Act Data
  • Restricted Reports
  • Sitemap