B-287449.2:
Jun 5, 2001
A firm protested a Department of the Interior contract award for building construction, contending that Interior improperly allowed the awardee to make an upward correction of its low bid. GAO held that Interior's decision to allow the awardee to upwardly correct its low bid was not objectionable, since Interior reasonably concluded that the awardee presented clear and convincing evidence of the c...