B-283172.2:
Oct 4, 1999
A firm protested the Army Corps of Engineers' rejection of its bid for transformers, contending that the Corps improperly determined that its descriptive literature failed to address the solicitation's requirements. GAO held that the Corps properly rejected the protester's bid for transformers as nonresponsive, since the bid, which include information on two transformers, did not indicate which t...