B-277235.2:
Nov 12, 1997
A firm protested an Army contract award for the inspection and repair of storm and sanitary sewer lines, contending that: (1) the awardee did not meet a definitive responsibility criterion; (2) the contracting officer improperly considered the qualifications of the awardee's subcontractor; and (3) there was not sufficient evidence to show that the subcontractor satisfied the criterion on the award...