[Request for Reimbursement of Protest Preparation Costs]

B-276030.2: Sep 12, 1997

A firm claimed reimbursement for its bid preparation and protest costs pursuant to its protest against a Navy solicitation for a Scaled Integrated Voice Communications System, contending that the Navy agreed to amend the solicitation in response to its protest. GAO held that the Navy did not act improperly. Accordingly, the claim was denied...

  • pdf icon View Decision (PDF, 5 pages)
Matter of: Spar Applied Systems--Declaration of Entitlement File: B-276030.2 Date: September 12, 1997

B-276030.2: Sep 12, 1997

DIGEST Request for recommendation that costs of filing and pursuing protest be reimbursed is denied. Where protest that the terms of a solicitation were ambiguous was not clearly meritorious. The SIVCS will be installed on Navy aircraft carriers and used as a prototype for the next generation of Navy integrated interior voice. The RFP added that the purpose of the SOW is to articulate a statement...

  • html report icon View Decision (HTML)
U.S. Government Accountability Office (GAO)
  • Press Center
  • Copyright & Terms of Use
  • FOIA Requests
  • Contact Us
  • Privacy Policy
  • Scam Alerts
  • Inspector General
  • Accessibility
  • No FEAR Act Data
  • Restricted Reports
  • Sitemap