The report you requested was not found, or there is more than one product with this report number. Please select from this list of similar report numbers.


[Protest of Army Contract Award for Detection System Engineering and Manufacturing Development]

B-275807.2: Apr 16, 1997

A firm protested an Army contract award for biological warfare agent detection system engineering and manufacturing development, contending that the Army: (1) made improper cost realism adjustments to its proposal; (2) unreasonably evaluated its technical proposal; (3) unreasonably concluded that there was no basis to discriminate between proposals in the area of performance risk; (4) unreasonably...

  • pdf icon View Decision (PDF, 14 pages)
Matter of: Litton Systems, Inc., Amecom Division File: B-275807.2 Date: April 16, 1997 * Redacted Decision

B-275807.2: Apr 16, 1997

DIGEST Protester's arguments that the cost realism adjustments made to its proposed costs were improper are denied where the record shows that the agency had a reasonable basis for its conclusions. Higher-probable cost proposal offered the best value to the government is denied where the record shows that the agency evaluation was reasonable and in accordance with the stated evaluation criteria. P...

  • html report icon View Decision (HTML)
U.S. Government Accountability Office (GAO)
  • Press Center
  • Copyright & Terms of Use
  • FOIA Requests
  • Contact Us
  • Privacy Policy
  • Scam Alerts
  • Inspector General
  • Accessibility
  • No FEAR Act Data
  • Restricted Reports
  • Sitemap