[Request for Reconsideration of Air Force Contract Award for Aircraft Maintenance]

B-275587.5,B-275587.6: Oct 14, 1997

A firm requested reconsideration of the dismissal of its protest against an Air Force contract award for programmed depot level maintenance (PDM) of the C-130 aircraft. GAO held that the Air Force would take corrective action in response to the protest within a reasonable period of time. In its request for reconsideration, the protester contended that the Air Force: (1) did not take corrective act...

  • pdf icon View Decision (PDF, 8 pages)
Matter of: Pemco Aeroplex, Inc.--Reconsideration and Costs File: B-275587.5; B-275587.6 Date: October 14, 1997

B-275587.5,B-275587.6: Oct 14, 1997

It becomes obvious that we will not be able to accomplish any of the scheduled FY 97 PDM . . . under contract. . . . . . . We need to be able to release the customer money which is currently obligated on the [Aero contract]. I have been advised by my Legal staff that due to requirements of the Anti-Deficiency Act. The only proper way to deobligate those funds which are currently obligated against...

  • html report icon View Decision (HTML)
U.S. Government Accountability Office (GAO)
  • Press Center
  • Copyright & Terms of Use
  • FOIA Requests
  • Contact Us
  • Privacy Policy
  • Scam Alerts
  • Inspector General
  • Accessibility
  • No FEAR Act Data
  • Restricted Reports
  • Sitemap