[Protest of NRC Rejection of Bid for Automated Property Management System]

B-272780: Oct 28, 1996

A firm protested the Nuclear Regulatory Commission's (NRC) rejection of its bid as technically unacceptable, contending that it should have been permitted to demonstrate the technical acceptability of its proposed software package. GAO held that NRC: (1) properly eliminated the protester's bid from the competition, since the protester failed to provide written documentation demonstrating complianc...

  • pdf icon View Decision (PDF, 4 pages)
Matter of: Inte-Great Corporation File: B-272780 Date: October 28, 1996

B-272780: Oct 28, 1996

The protester contends that it should have been permitted to make an oral presentation to demonstrate the technical acceptability of its proposed software package. Which was issued on April 5. Offerors were instructed that prior to the time set for receipt of initial proposals under the RFP. They should submit to the NRC "a matrix showing how each NRC mandatory requirement is satisfied in the prop...

  • html report icon View Decision (HTML)
U.S. Government Accountability Office (GAO)
  • Press Center
  • Copyright & Terms of Use
  • FOIA Requests
  • Contact Us
  • Privacy Policy
  • Scam Alerts
  • Inspector General
  • Accessibility
  • No FEAR Act Data
  • Restricted Reports
  • Sitemap