B-272430:
Oct 8, 1996
A firm protested the Army Corps of Engineers' rejection of its bid and subsequent contract award for dormitory construction, contending that the Corps improperly rejected its bid as nonresponsive, since the facsimile copy of its bid bond met the solicitation's requirements. GAO held that the: (1) facsimile copy of the bid bond did not satisfy the bid bond requirement, since the original bond could...