[Protest of Navy Solicitation for Carbine Suppressors]

B-271835: Jul 31, 1996

A firm protested a Navy solicitation for carbine sound and flash suppressors, contending that the: (1) Navy failed to allow adequate time for bidders to submit bid samples; (2) Navy improperly downgraded the performance specifications to accommodate a particular bidder; and (3) solicitation improperly penalized bidders with state-of-the-art designs. GAO held that the: (1) protester had adequate ti...

  • pdf icon View Decision (PDF, 5 pages)
Matter Of: OPS, Inc. File: B-271835 Date: July 31, 1996

B-271835: Jul 31, 1996

Protest that agency did not permit sufficient time for offerors to submit product samples is denied where the agency permitted more than the statutorily required 30 days. Adequate competition was expected. There is no indication that the agency deliberately attempted to exclude the protester from the procurement and. The protester was made aware of the general requirement more than 4 months before...

  • html report icon View Decision (HTML)
U.S. Government Accountability Office (GAO)
  • Press Center
  • Copyright & Terms of Use
  • FOIA Requests
  • Contact Us
  • Privacy Policy
  • Scam Alerts
  • Inspector General
  • Accessibility
  • No FEAR Act Data
  • Restricted Reports
  • Sitemap