[Protest of GPO Bid Rejection]
B-270787: Dec 29, 1995
Additional Materials:
- Full Report:
Contact:
A firm protested the Government Printing Office's rejection of its bid as nonresponsive, contending that it should not have been required to submit a certificate of procurement integrity. GAO held that: (1) GPO properly rejected the protester's bid as nonresponsive, since the protester failed to provide a certificate of procurement integrity; and (2) the protester untimely filed after bid opening its protest of alleged solicitation improprieties. Accordingly, the protest was dismissed.
Jan 25, 2021
-
Crowley Government Services, Inc.; Petro Star, Inc.
We sustain the protests.
B-419347,B-419347.2,B-419347.3 -
-
-
-
Jan 22, 2021
Jan 21, 2021
Jan 19, 2021