B-270102,B-270102.2:
Feb 8, 1996
A firm protested an Army Corps of Engineers contract award for warehouse and storage facility construction, contending that the Corps: (1) made an unreasonable price-technical tradeoff; and (2) improperly conducted discussions with only the awardee. GAO held that the: (1) Corps reasonably determined that, while the difference in the bidders' technical scores was negligible, the difference in their...