[Protest of Army Bid Rejection]
B-265646: Aug 15, 1995
Additional Materials:
- Full Report:
Contact:
A firm protested the Army's rejection of its bid, contending that the Army improperly excluded its bid from the competitive range. GAO held that the: (1) protester failed to provide a valid basis of protest; and (2) protest was premature, since the protester had not yet requested a debriefing on the reasons its bid was excluded. Accordingly, the protest was dismissed.