[Protest of Army Corps of Engineers Bid Rejection]

B-262142: Aug 28, 1995

Additional Materials:

Contact:

Office of Public Affairs
(202) 512-4800
youngc1@gao.gov

A firm protested the Army Corps of Engineers' rejection of its bid, contending that the Corps improperly rejected its bid as nonresponsive, since it had 45 days after the bond's execution to meet the surety limitation. GAO held that the protester: (1) untimely filed its protest more than 10 days after it knew the basis of protest; and (2) had constructive notice of the applicable procurement regulation prior to the Corps' rejection of its bid. Accordingly, the protest was dismissed.

Sep 16, 2019

Sep 13, 2019

Sep 12, 2019

  • TCG, Inc.
    We dismiss the protest in part and deny the protest in part.
    B-417610,B-417610.2

Sep 11, 2019

Sep 10, 2019

Sep 9, 2019

Looking for more? Browse all our products here