[Protest of USDA Delivery Order for Financial Management System Support and Enhancement]

B-261070: Jun 9, 1995

Additional Materials:

Contact:

Office of Public Affairs
(202) 512-4800
youngc1@gao.gov

A firm protested a Department of Agriculture (USDA) delivery order for financial management system support services, contending that USDA: (1) improperly awarded the delivery order to the awardee, since it submitted the low bid; and (2) evaluated the bids on the basis of unstated evaluation criteria. GAO held that: (1) USDA properly rejected the protester's bid as nonresponsive, since the protester failed to indicate its total bid price; and (2) the protester untimely filed after bid opening its protest of alleged defective specifications. Accordingly, the protest was dismissed.

Oct 29, 2020

Oct 28, 2020

Oct 27, 2020

  • Silver Investments, Inc.
    We dismiss the protest as untimely because it was filed more than 10 days after the protester knew, or should have known, the basis for its protest.
    B-419028

Looking for more? Browse all our products here