B-260801 Published: Mar 28, 1995. Publicly Released: Mar 28, 1995.
Jump To:
Skip to Highlights

Highlights

A firm protested the Army's rejection of its bid, contending that the Army: (1) improperly rejected its bid for failing to include a bid bond in the required amount; and (2) did not provide adequate time to respond to the solicitation. GAO held that the protester untimely filed its protest after bid opening. Accordingly, the protest was dismissed.