B-260778.4:
Jul 8, 1996
A firm requested reconsideration of its denied protests of an affirmed Air Force contract award for deployable integrated mobile hospital tent systems. GAO had held that the: (1) Air Force reasonably determined that the awardee met the solicitation's definitive responsibility criteria; (2) Air Force reasonably determined that the awardee was financially capable of performing the contract; and (3)...