[Protest of Subcontract Award]

B-260196: Jan 27, 1995

Additional Materials:


Office of Public Affairs
(202) 512-4800

A firm protested a government subcontract award. GAO held that it would not consider the prime contractor's subcontract award, since the government was not substantially involved in the procurement. Accordingly, the protest was dismissed.

Mar 15, 2018

  • ORBIS Sibro, Inc.
    We sustain the protest in part and deny it in part.