[Claim for Withdrawal from BOP Contract Due to Bid Error]

B-259048: Nov 4, 1994

Additional Materials:


Office of Public Affairs
(202) 512-4800

A firm requested that the Federal Bureau of Prisons allow it to withdraw its post-award bid for a radiologist, contending that it had made a mistake in its proposed price. GAO held that the awardee's post-award mistake concerned a matter of contract administration, which it would not review. Accordingly, the protest was dismissed.