[Protest of Air Force Allowance of Bid Correction]

B-258792: Dec 6, 1994

Additional Materials:

Contact:

Office of Public Affairs
(202) 512-4800
youngc1@gao.gov

A firm protested the Air Force's decision to allow a bidder the opportunity to correct its bid under a solicitation for base power supply repairs. GAO held that the protester untimely filed its protest more than 10 days after it learned the basis of protest. Accordingly, the protest was dismissed.