[Protest of Army Contract Award for Guidewall Construction]

B-258205 Published: Dec 20, 1994. Publicly Released: Dec 20, 1994.
Jump To:
Skip to Highlights

Highlights

A firm protested an Army contract award for waterway guidewall construction, contending that the Army: (1) improperly determined that the awardee's bid was responsive; and (2) mistakenly assumed that the Buy American Act did not apply to the procurement. GAO held that the: (1) protester's contention that the Army considered the Act inapplicable was based solely on the inaccurate statement of an unauthorized Army employee; (2) protester failed to provide a valid basis of protest; and (3) protester untimely filed after bid opening its protest of alleged solicitation improprieties. Accordingly, the protest was dismissed.

Office of Public Affairs

Topics

Army procurementBid responsivenessBuy national policyConstruction contractsContract award protestsIntercoastal waterwaysSpecifications protestsUntimely protestsU.S. ArmyBid evaluation protestsConstruction