[Request for Reconsideration of Dismissed Protest]
B-256187.2
Published: May 26, 1994. Publicly Released: May 26, 1994.
Skip to Highlights
Highlights
A firm requested reconsideration of its dismissed protest of a Department of Transportation contract award. In its request for reconsideration, the protester reiterated its original arguments and disagreed with the original decision. GAO held that the protester failed to present any evidence that warranted the reversal of its original decision. Accordingly, the request for reconsideration was denied.