[Protest of Army Contract Modification]

B-252359.4: Sep 23, 1994

Additional Materials:

Contact:

Office of Public Affairs
(202) 512-4800
youngc1@gao.gov

A firm protested the modification of an Army contract after award. GAO held that the: (1) protest concerned a matter of contract administration which it would not consider; (2) Army properly determined that the modification was needed because of a mutual mistake regarding the incorporation of a wage determination into the contract; and (3) protester was not prejudiced by the contract modification, since the awardee remained the technically superior, low bidder. Accordingly, the protest was dismissed.

Apr 23, 2018

Apr 20, 2018

Apr 18, 2018

Apr 17, 2018

  • AeroSage, LLC
    We dismiss in part and deny in part the protests.
    B-415893,B-415894

Apr 16, 2018

Looking for more? Browse all our products here