[Protests of DOE Subcontract Award for Computer Systems]

B-249421,B-249422,B-249423,B-249424,B-249425: Nov 23, 1992

Additional Materials:

Contact:

Office of Public Affairs
(202) 512-4800
youngc1@gao.gov

A firm protested a Department of Energy (DOE) subcontract award for computer systems, contending that: (1) DOE improperly applied a price differential to its bid based on provisions of the Buy American Act; and (2) the awardees did not offer systems with the requisite Federal Communications Commission certification. GAO held that the: (1) DOE prime contractor made an improper determination regarding the domestic status of the awardees' equipment without considering the place of manufacture for the products; and (2) protester untimely filed its protest concerning product certification. Accordingly, the protest was sustained in part and dismissed in part.

Oct 29, 2020

Oct 28, 2020

Oct 27, 2020

  • Silver Investments, Inc.
    We dismiss the protest as untimely because it was filed more than 10 days after the protester knew, or should have known, the basis for its protest.
    B-419028

Looking for more? Browse all our products here