B-246080:
Feb 26, 1992
A firm protested an Army Corps of Engineers contract award for rehabilitation work, contending that the: (1) Army improperly permitted the awardee to correct its bid error; (2) awardee's corrected and original bids were unreasonably low; and (3) awardee was not responsible. GAO held that: (1) the Army properly permitted the awardee to correct its bid error, since the awardee's original bid prepara...