[Request for Protest Costs Pursuant to Protest of Air Force Sole-Source Procurement]

B-242650.7: Feb 13, 1997

A firm claimed reimbursement for its protest costs pursuant to its sustained protest of an Air Force sole source procurement for public utility service. GAO held that: (1) the claimant could recover in-house costs directly related to its protest; (2) the claimant did not sufficiently document two of its company officers' work on the protest; (3) the third officer's calendar diary entries were suff...

  • pdf icon View Decision (PDF, 3 pages)
Matter of: Gulf Gas Utilities Co.--Claim for Costs File: B-242650.7 Date: February 13, 1997

B-242650.7: Feb 13, 1997

Is allowed for that portion of the claim for which the protester has provided sufficiently detailed documentation to support the claim. We determine that Gulf Gas is entitled to recover $9. Was not sufficiently detailed. Reimbursement of costs is allowed where the protester has submitted sufficient documentary evidence to support them and where these costs. Are shown to be reasonable and necessary...

  • html report icon View Decision (HTML)
U.S. Government Accountability Office (GAO)
  • Press Center
  • Copyright & Terms of Use
  • FOIA Requests
  • Contact Us
  • Privacy Policy
  • Scam Alerts
  • Inspector General
  • Accessibility
  • No FEAR Act Data
  • Restricted Reports
  • Sitemap