B-241391.3:
May 20, 1991
A firm requested reconsideration of its denied protest against the Air Force's rejection of its late bid for transformer replacement. GAO held that the protester: (1) did not provide any evidence warranting reversal or modification of the prior decision; and (2) untimely raised arguments that it could have raised in its original protest. Accordingly, the request for reconsideration was denied...