[Protest of GSA Rejection of Unsolicited Proposal]

B-239581,B-239582,B-239584: Jun 4, 1990

Additional Materials:


Office of Public Affairs
(202) 512-4800

A firm protested the General Services Administration's (GSA) rejection of its unsolicited proposal for a cost-comparison study of motor vehicle fleet management services, contending that GSA: (1) improperly rejected its proposal; and (2) failed to comply with the applicable procurement laws and regulations. GAO held that the protester untimely: (1) filed its protest more than 10 days after it knew the basis for protest; and (2) protested alleged solicitation improprieties. Accordingly, the protest was dismissed.

Mar 22, 2018

Mar 20, 2018

Mar 19, 2018

  • Ampcus, Inc.
    We deny the protest.
  • AMAR Health IT, LLC
    We dismiss the protest because our Office does not have jurisdiction to entertain protests of task orders issued under civilian agency multiple-award, indefinite-delivery, indefinite-quantity (IDIQ) contracts that are valued at less than $10 million.
  • Centurum, Inc.--Costs
    We grant the request.

Mar 15, 2018

  • ORBIS Sibro, Inc.
    We sustain the protest in part and deny it in part.