B-239075:
Jul 24, 1990
A firm protested a Navy contract award for replacement decking, contending that the: (1) Navy failed to conduct the procurement on an equal basis, since it provided offerers different information and the solicitation was ambiguous; and (2) most cost-effective ordering plan rendered the evaluation meaningless. GAO held that the protester: (1) failed to show that the Navy provided offerers different...