[Protest of Any UNICOR Contract Award for Connector Plugs]

B-237794: Feb 23, 1990

A firm protested a Federal Prison Industries (UNICOR) contract award to any other bidder for connector plugs, contending that: (1) UNICOR improperly rejected its low bid; and (2) the solicitation did not mention a qualified products list (QPL). GAO held that UNICOR unreasonably: (1) rejected the protester's bid, since solicitation did not identify the procurement as restricted to QPL products; and...

  • pdf icon View Decision (PDF, 5 pages)
B-237794, Feb 23, 1990

B-237794: Feb 23, 1990

Connecticut. /1/ UNICOR rejected Comspace's bid on the basis that Comspace was not listed as an offeror of products on a qualified products list (QPL) at bid opening. The protester basically alleges that the IFB did not identify the acquisition as subject to a qualification requirement and that it was not made aware of the QPL requirement prior to bid opening. Five bids were received by bid openin...

  • html report icon View Decision (HTML)
U.S. Government Accountability Office (GAO)
  • Press Center
  • Copyright & Terms of Use
  • FOIA Requests
  • Contact Us
  • Privacy Policy
  • Scam Alerts
  • Inspector General
  • Accessibility
  • No FEAR Act Data
  • Restricted Reports
  • Sitemap