B-237779:
Mar 22, 1990
A firm protested an Air Force subcontract award for site surveys, contending that: (1) the prime contractor acted as the government's agent in awarding the subcontract; and (2) since the required work was outside the scope of the prime contract, the subcontract was for the government. GAO held that the prime contractor: (1) was not providing management or purchasing services for the government; an...