[Protest of Army Contract Award for HVAC Piping Repair or Replacement]
https://www.gao.gov/products/140745

B-237361: Feb 16, 1990

A firm protested an Army contract award for piping repair or replacement, contending that the Army improperly calculated bid prices in determining the low bidder. GAO held that the: (1) Army properly evaluated the protester's bid in accordance with the solicitation's price evaluation formula; and (2) protester untimely filed after bid opening its protest against apparent solicitation improprieties...

  • pdf icon View Decision (PDF, 3 pages)
B-237361, Feb 16, 1990
https://www.gao.gov/products/437438

B-237361: Feb 16, 1990

Is untimely when first raised by protester after bid opening. The award was made under invitation for bids (IFB) DAKF10-89-B- 0104 for the repair or replacement of HVAC piping at Pinwheel Barracks. There were four additive bid items for additional areas in each building. Provides that award will be made to the bidder offering the low aggregate amount for the base bid item. Since sufficient funds w...

  • html report icon View Decision (HTML)
U.S. Government Accountability Office (GAO)
  • Press Center
  • Copyright & Terms of Use
  • FOIA Requests
  • Contact Us
  • Privacy Policy
  • Scam Alerts
  • Inspector General
  • Accessibility
  • No FEAR Act Data
  • Restricted Reports
  • Sitemap