B-237139:
Jan 5, 1990
A firm protested a proposed Air Force contract award for interior painting and carpeting, contending that the proposed awardee's bid was nonresponsive, since it quoted a single price and submitted separate line-item prices only after bid opening. GAO held that the proposed awardee's failure to timely break down the separate line-item prices was a minor informality not requiring rejection of its bi...