B-236784.2:
May 25, 1990
A firm requested reconsideration of its protest against the Army Corps of Engineers' rejection of its bid as nonresponsive. GAO had held that the Corps could not reasonably infer the protester's intended bid price, which was a condition for allowing correction. In its request for reconsideration, the protester contended that: (1) the Corps could have inferred its bid price from another bid option;...