B-236294:
Nov 21, 1989
A firm protested a Navy contract award for communications equipment, contending that the Navy: (1) failed to consider whether the awardee's bid was unrealistically low, given its reliance on unproven technology; (2) should have informed it that its bid was too high; and (3) should have reopened discussions to evaluate its alternate proposal. GAO held that the Navy: (1) reasonably awarded the contr...