B-235620:
Aug 21, 1989
A firm protested the Navy's rejection of its bid for hangar modification, contending that the Navy unreasonably determined that its sureties were not responsible. GAO held that the Navy reasonably concluded from the available information and surety representations that the sureties failed to clearly establish their responsibility and net worth. Accordingly, the protest was denied...