[Protest of Navy Rejection of Bidder as Nonresponsible]
https://www.gao.gov/products/139305

B-235324: Aug 10, 1989

A firm protested the Navy's rejection of its bid for building repair and alteration, contending that the Navy improperly determined that its sureties were not responsible. GAO held that the Navy reasonably based its nonresponsibility determination on: (1) the protester's failure to provide sufficient information for verifying the sureties' financial resources; and (2) an ongoing criminal investiga...

  • pdf icon View Decision (PDF, 5 pages)
B-235324, Aug 10, 1989, 89-2 CPD 124
https://www.gao.gov/products/420791

B-235324: Aug 10, 1989

PROCUREMENT - Contractor Qualification - Responsibility - Contracting officer findings - Negative determination - GAO review PROCUREMENT - Sealed Bidding - Bid guarantees - Sureties - Acceptability - Information submission DIGEST: Contracting agency reasonably found that bidder was nonresponsible based on a finding that the bidder's individual sureties on its bid bond were unacceptable due to bidd...

  • html report icon View Decision (HTML)
U.S. Government Accountability Office (GAO)
  • Press Center
  • Copyright & Terms of Use
  • FOIA Requests
  • Contact Us
  • Privacy Policy
  • Scam Alerts
  • Inspector General
  • Accessibility
  • No FEAR Act Data
  • Restricted Reports
  • Sitemap