[Protests of Army Corps of Engineers Rejection of Bids for General Repairs and Steam Modernization Projects]

B-232986,B-232987,B-232988: Feb 9, 1989

Additional Materials:


Office of Public Affairs
(202) 512-4800

A firm protested the Army Corps of Engineers' rejection of its low bid for general repairs and steam modernization projects, contending that: (1) its sureties' net worth was sufficient, and it provided adequate documentation thereof; and (2) the Corps did not provide it sufficient time to furnish additional documentation on its sureties' net worth. GAO held that the: (1) Corps reasonably found the protester's bid unacceptable, since it could not verify the individual sureties' financial resources and net worth; and (2) protester untimely protested the allegedly insufficient time to submit additional information. Accordingly, the protest was denied.

Mar 15, 2018

  • ORBIS Sibro, Inc.
    We sustain the protest in part and deny it in part.

Mar 14, 2018

Mar 13, 2018

Mar 12, 2018

Mar 9, 2018

Mar 7, 2018

Looking for more? Browse all our products here