B-232746:
Jan 19, 1989
A firm protested a Navy delivery order under a schedule contract for magnetic cleaner, contending that the: (1) Navy improperly issued the purchase order on a sole-source basis; (2) Navy's technical requirements exceeded its minimum needs; and (3) Navy improperly accepted the awardee's discounted prices. GAO held that the: (1) protester failed to show that award to the only firm meeting the Navy's...