B-232289:
Nov 7, 1988
A firm protested a Marine Corps contract award for video system sets, contending that the Corps should have rejected the awardee's bid as nonresponsive, since the Corps had informed the protester during a previous solicitation that it would not consider modified products. GAO held that the Corps: (1) properly determined that the awardee's product complied with its specifications; and (2) did not p...