[Protest of USMC Contract Award for Video System Sets]

B-232289: Nov 7, 1988

A firm protested a Marine Corps contract award for video system sets, contending that the Corps should have rejected the awardee's bid as nonresponsive, since the Corps had informed the protester during a previous solicitation that it would not consider modified products. GAO held that the Corps: (1) properly determined that the awardee's product complied with its specifications; and (2) did not p...

  • pdf icon View Decision (PDF, 3 pages)
B-232289, Nov 7, 1988, 88-2 CPD 450

B-232289: Nov 7, 1988

PROCUREMENT - Sealed Bidding - Bids - Responsiveness - Determination criteria DIGEST: Protest that awardee's bid is nonresponsive is denied where the awardee has unequivocally offered to provide the required video system in conformity with all material terms and conditions of the invitation for bids. Oscar Vision contends that CTL's bid is not responsive to the IFB. The IFB was for 820 video syste...

  • html report icon View Decision (HTML)
U.S. Government Accountability Office (GAO)
  • Press Center
  • Copyright & Terms of Use
  • FOIA Requests
  • Contact Us
  • Privacy Policy
  • Scam Alerts
  • Inspector General
  • Accessibility
  • No FEAR Act Data
  • Restricted Reports
  • Sitemap