[Protest of Subcontract Award Under Air Force Contract for Strobe Lights]

B-231414: Jun 21, 1988

A firm protested a subcontract award for strobe lights under an Air Force prime contractor solicitation, contending that the prime contractor: (1) did not disclose the evaluation criteria; and (2) improperly evaluated its bid. GAO held that the subcontract was not awarded by or for the federal government. Accordingly, the protest was dismissed...

  • pdf icon View Decision (PDF, 3 pages)
B-231414, Jun 21, 1988, 88-1 CPD 594

B-231414: Jun 21, 1988

PROCUREMENT - Special Procurement - Methods/Categories - Subcontracts - Contract awards - GAO review DIGEST: Protest of a subcontract awarded by a government prime contractor is dismissed where the subcontract was not "by or for" the government. That the evaluation of FL Aerospace's proposal was not fair. We dismiss the protest because the subcontract was not awarded by or for a federal agency. We...

  • html report icon View Decision (HTML)
U.S. Government Accountability Office (GAO)
  • Press Center
  • Copyright & Terms of Use
  • FOIA Requests
  • Contact Us
  • Privacy Policy
  • Scam Alerts
  • Inspector General
  • Accessibility
  • No FEAR Act Data
  • Restricted Reports
  • Sitemap