B-230864:
Jun 23, 1988
A firm protested the Air Force's rejection of its bid for asbestos removal, contending that the Air Force: (1) did not allow it sufficient time to obtain acceptable sureties for bid bonds; (2) arbitrarily and selectively enforced regulations concerning acceptance of individual sureties; and (3) failed to inform it of the difficulties it experienced in verifying the sureties' statements. GAO held t...