B-230855:
Apr 8, 1988
A firm protested the Federal Aviation Administration's (FAA) procurement procedures under a solicitation for towers, contending that: (1) FAA should have procured the towers under the protester's current contract with the Department of Transportation; and (2) the towers FAA solicited were obsolete, expensive, and inefficient. GAO held that the protester untimely filed its protest more than 10 days...