B-230769.2:
Apr 1, 1988
A firm protested a subcontract award for school construction under a Bureau of Indian Affairs contract, contending that the proposed awardee improperly revised its bid after bid opening. GAO held that the protester was not sufficiently interested to challenge the award, since it was not an actual or prospective bidder. Accordingly, the protest was dismissed...