[Protest of Forest Service Contract Award for Helicopters]

B-230724.4: Aug 1, 1988

A firm protested a Forest Service contract award for helicopters, contending that the awardee's bid was nonresponsive, since its helicopters exceeded the Federal Aviation Administration's (FAA) maximum weight limitation. GAO held that the: (1) awardee's bid was responsive, since the awardee did not limit or modify its obligation to supply acceptable helicopters; and (2) Service reasonably determin...

  • pdf icon View Decision (PDF, 3 pages)
B-230724.4, Aug. 1, 1988, 88-2 CPD 104

B-230724.4: Aug 1, 1988

PROCUREMENT - Sealed Bidding - Bids - Responsiveness - Determination criteria DIGEST: A bid to provide a helicopter for fighting fires and other services is responsive where the bid does not qualify or limit the offeror's obligation to supply a helicopter that is below the maximum weight limitation certified by the Federal Aviation Administration. The IFB contained 11 line items representing the v...

  • html report icon View Decision (HTML)
U.S. Government Accountability Office (GAO)
  • Press Center
  • Copyright & Terms of Use
  • FOIA Requests
  • Contact Us
  • Privacy Policy
  • Scam Alerts
  • Inspector General
  • Accessibility
  • No FEAR Act Data
  • Restricted Reports
  • Sitemap